Document 02·Application draft
The application, section by section.
The working draft of the SWITCH-Asia application, held jointly by both teams. It reads in order; every number still owed is marked in amber, with the owner's name beside it.
§0Identification
| Working title | CIRCULAR LAMPUNG — Demonstrating plastic-waste pyrolysis for circular petrochemical feedstock in Bandar Lampung, Indonesia |
| Priority | Priority 1 — sustainable production |
| Sector | Plastics, with focus on plastic packaging and its waste |
| Action location | Bandar Lampung, Lampung Province, Indonesia — principal country: Indonesia |
| Duration | 36 months |
| Total budget | USD 2,500,000 |
| Requested from EU | USD 2,000,000 — 80% of eligible costs |
| Co-financing | USD 500,000 — 20%, from Genco and EE own resources contributed 1:1, non-EU sources |
| Lead applicant | Elevated Elements Pte Ltd, Singapore |
| Co-applicants | Genco Oil Limited, Hong Kong · PT CEAA, Indonesia |
| SDG targets | 12.4 sound management of chemicals and wastes · 12.5 waste generation substantially reduced through prevention, recycling and reuse · 13.2 climate change measures integrated into policies and planning |
Contents
The application is organised as six numbered sections. Relevance makes the case for the problem and the fit; action design sets out what will actually be built and done; partnership, sustainability, budget and logframe then pin the same project down from four different angles — who delivers it, how it survives the grant, what it costs, and how success is measured.
Working assumptions
Four assumptions carry the draft, and each is being closed before submission. The feedstock stream is expected to be confirmed non-hazardous by the characterisation study, with a QC exclusion spec enforced at intake. UKL-UPL — Indonesia's standard environmental permit, rather than the full AMDAL impact assessment — is expected to be the applicable class, to be confirmed by the consultant's screening memo. The grant ceiling is assumed to accommodate a USD 2.0M ask, and if it does not, the budget is re-phased without changing the project logic. And the partnership eligibility rules of the new call are assumed to match the 2023 pattern, with the action-country requirement satisfied by PT CEAA.